Critical Path Method - Backward Pass

Опубликовано: 05 Декабрь 2021
на канале: De Ceuster Academy
971
40

Critical Path Method - Backward Pass

Once we complete the Early start, we found the ES and EF of all activities and found the project duration given by the EF of the last activities or activities without successors. In case there are more activities without successors, the project duration is given by the highest EF time.

The backward pass is when we calculate back from the project end date (eventually the project end date given by the project duration). The LF time of an activity is the latest time an activity can finish without changing the project duration, the LS time is the latest time an activity can start without changing the duration of the project.


Смотрите видео Critical Path Method - Backward Pass онлайн, длительностью часов минут секунд в хорошем качестве, которое загружено на канал De Ceuster Academy 05 Декабрь 2021. Делитесь ссылкой на видео в социальных сетях, чтобы ваши подписчики и друзья так же посмотрели это видео. Данный видеоклип посмотрели 971 раз и оно понравилось 40 посетителям.